KoalaTracker is Australia's national koala map and database, mapping the location of koala populations, points of impact and causes of death and injury for the public record. KoalaTracker empowers localised advocacy, enables more effective risk mitigation, adds to research and engages the community to save the koala. This blog discusses the knowledge gained through member submissions, koala mapping and location intelligence, scientific research and government action. Please join the conversation.

People v Powerlink KoalaTracker Blog
Alex Harris - Saturday, April 10, 2010

Does the Powerlines Action Group Eumundi (PAGE) really have a case against Powerlink, the government corporation responsible for the construction and maintenance of high voltage transmission lines? There is no question the quality of power supply to the northern end of the Sunshine Coast and hinterland is sub-standard and on the plus side, new high voltage transmission lines will smooth the spikes. On the negative, it will also deliver the infrastructure necessary for the government's desired doubling of population in the area. But wait, there's more...

I personally have been impressed with how Powerlink has engaged the community in other areas, and how it has worked to alleviate community concerns and adapted its plans to fit community requirements. But none of that commendable citizenship is visible to the residents of the community in this case. The relationship between PAGE and Powerlink, founded without consultation, has soured irrevocably.

There are several issues at stake, and I find the PAGE arguments compelling. They raise some important questions for us all.

Firstly, PAGE has documents detailing the easement now claimed over their properties by Powerlink as part of its high voltage transmission infrastructure, that will require clearing of an area 60m wide on some of these properties; that requires multiple access tracks from various directions for maintenance the length of the transmission, each around 8m wide, and that will install high voltage towers within 30m of houses of young families. The easement impacts 20-plus privately owned properties. It begs the question, why? Why this route?

This is not a situation of people buying next to the airport and then complaining about the noise. There was no easement marked over the lots showing major power line infrastructure, until now. What precedent does this set for other projects? What security do any of us have over our own properties, if the government can take easements over whatever part they want?

There is currently a major highway infrastructure upgrade underway that essentially links the same points that this new power infrastructure seeks to do. PAGE is arguing that Powerlink should install the power lines along the new highway upgrade, enabling a much shorter route with significantly less construction and significantly lower maintenance costs with obvious ease of access. From what I understand of the documents I have read, Powerlink argues this is not an option, nor is there any room. PAGE has a letter from Main Roads stating that it is an option and that they would happily work with Powerlink on a combined infrastructure corridor.

"The Department of Transport and Main Roads has no objection to Powerlink running a transmission line in a separate corridor adjacent to the Bruce Highway. Main Roads is working with Powerlink to align some sections of the new Cooroy to Curra highway corridor adjacent to existing Powerlink easements to minimise the cumulative effect on the community. This is the case in the section between Tandur Road, near the Matilda Service Station at Kybong and Six Mile Creek, just south of Gympie."

The only catch is that Powerlink "would need to acquire an additional corridor beside the highway for their high voltage transmission line."  I'm guessing this is what makes the option to divert away from the highway to go through pristine forest on privately held land, more attractive. But as the chosen path is over forested, mountainous terrain and makes the loop back to the highway a longer path overall (yes, it rejoins the highway), is this really a less expensive option? And does it take into account the cost to the environment?

The affected properties are in the hills behind Eumundi, with underground springs, creeks and other waterways that form the headwaters of the Maroochy River. Several properties in the line of fire were deemed by the old Maroochy Council to be of such significant ecological importance to the Maroochy River, they were the subject of council waterways rehabilitation and protective planting.

Some hold tracts of untouched forest with 35m+ trees. All hold endangered wildlife, including an apparently healthy population of koalas. The people who bought these properties did so for these reasons. Some have been there decades, some only a few years. All are as one for the environment in which they live, wanting to preserve and protect the land. Most properties in the area are listed as Land for Wildlife - giving them a status of protected reserve under state government legislation. The government's own Land for Wildlife website claims it is a vibrant, progressive program that aims to protect native wildlife and flora for the benefit of future generations. It states: "to-date over 46,000 hectares of habitat for wildlife has been protected with a further 2800 hectares under restoration."

Earth to the Qld government: It is not protected if you allow infrastructure construction in the middle of it. Included below are a handful of photos taken on the properties in Powerlink's path. Click on one to be taken to the complete photogallery. Note the size of the people against the trees in some of the photos. There are 25 photos in all.

First six images courtesy Carlos Sanchez
Next

Powerlink argues that it will not impact koalas, as this area is not mapped as koala habitat by the state government. Actually, it appears to have been left off the habitat map entirely. But the state's habitat mapping - which relies on the remote digital analysis of aerial image pixels (pertaining to trees) - bears almost no relationship to the whereabouts of koalas. As the photos above show, regardless of whether the area is mapped as high-value habitat or not, it is without question important koala habitat. 

The 60m wide easement, says Powerlink, applies only to the last 8km leading to the substation - right through the middle of these Land for Wildlife properties.

The Qld government has made known its intent and desire to double our population. Powerlink, as a government corporation, has budgetary and political pressures that make this front and centre a state government decision, not one of an independent corporation. How then, can the same state government that has agreed these properties are deserving of protective status, allow the northern most population of the Richmond Birdwing Butterfly and a healthy koala population to be subjected to such extensive earthworks and loss of habitat, at its own hand?

With a doubling of population the government's intent, the situation faced by PAGE - representative of the residents who will soon be forced to live under high voltage towers with a 60m wide clearing through their properties - it seems could be faced by any one of us, at any time.

How is that possible in a democracy? Mostly because the silent majority remains just that. And yes, putting myself in the shoes of residents in Eerwah Vale, West Cooroy and Eumundi, I believe they have a good case against power lines taking a path through their properties.

Resources:

Watch: A video of the area produced by PAGE

Watch: The story on Channel 7

Watch: Beach protest Easter Saturday

To learn more: http://www.saveeumundi.org/powerlinks-project/



Comments

You need to be logged in before you can comment (see login at top of screen). If not a member REGISTER HERE. Membership access is immediate. Please maintain respect for each other's views. The editor reserves the right to edit (for any reason) or block an inappropriate comment. Thank you.

Anonymous commented on 12-Apr-2010 12:28 PM
“The proposed new easements between Ridgewood and Eerwah Vale , being 8.5km in length, will require 0.45ha of mapped koala vegetation to be cleared for the new transmission line” (stated by Powerlink in the Noosa News April 9 2010.) This, despite there being koala habitat and vegetation along and nearby the entire 8.5km. It is very convenient for Powerlink that this significant koala habitat has been left off the mapping. Powerlink fail to mention though, that 8 metre access tracks will be required to every pole, and because of the steep and inaccessible terrain, their construction will require many more kilometres of clearing thru this prime koala vegetation. Stringing lines above the canopy will not stop the need for these access tracks to be constructed.
Come clean Powerlink, can’t you see that the route along the hwy as proposed by PAGE, is far less detrimental to the environment, families and businesses? Keep government owned infrastructure on government owned land and save the Noosa Hinterlands valuable habitat for its healthy koalas and wildlife.
Cathy Fitzgerald commented on 12-Apr-2010 06:09 AM
Thanks Alex a great article. In recent comments by powerlink they say they are going to over hang the powerlines over the Koala habitat but what they don't mention is the destruction that will occur from the access tracks and easements. Whats your story powerlink why are you so hell bent on destroying the environment???? Start being honest and listen to the people you might be suprised where it takes you. Why not be known as the company that saved the environment rather then destroyed it. I would have thought that for the future of the company this would bring better outcomes.
Joe Russell commented on 11-Apr-2010 03:51 PM
If the contractors laying the new pipeline alongside the Bruce Highway at Eumundi can do that without problems and interuption to daily traffic, why can't Powerlink undertake the same type civil engineering project to bury their cables? The pipeline contractors are not using any more land than is available on the side of the motorway. Seems logical to me, as a retired engineer!
Anonymous commented on 11-Apr-2010 02:42 PM
A well written comment, and obviously well researched. As a resident in the Eerwah Vale area, I have personal knowledge about this Powerlink Project. One thing that Alex didn't say is that many of the proposed towers are planned to be constructed on a 55 degree slope. This is the reason why Powerlink will forcibly acquire vast tracts of forest and good quality agricultural land to make 8m wide access tracks from tower to tower. One would naturally imagine that an easement is acquired to provide for the construction of AND to be able to service, whatever the infrastructure is. Why then, is any corporation, state-owned or otherwise, allowed to ignore a less costly, less impacting socially and environmentally decision, and irrevocably destroy land and private properties for the sake of "not wanting to change their initial decision". The Minister for Mines and Energy must put a halt to this "not-fit-for-purpose" project as it currently stands and genuinely consider using a common infrastructure corridor. This is after all, What Premier Bligh states in her Towards Q2 and the SEQ Infrastructure Plan and Programme (SEQIPP) "The SEQ Infrastructure Plan seeks to maximise the use of existing infrastructure and ensure that the associated planning, development and operation of new projects minimise the demand they make on resources..." This same document under the heading of Infrastructure Priorities states "Other factors considered when prioritising infrastructure projects are those supporting quality of life and community wellbeing". These types of statements enshrined in state government departments' policy documents are totally at odds with Powerlink's project. Why, Premier Bligh? Just explain why.
carlos sanchez commented on 11-Apr-2010 01:44 PM
Good on you Alex. I don't think you could have described the situation better than that. What people don't realise is what a substation is for. This is to distribute more powerlines, and guess where those ones would be going to?? To the coast, meaning more easements, and more destruction. Hope people start thinking about it, because I guess, those new lines would be on paper by now.

Post a Comment




Captcha Image


Previous Next





CONNECT ON TWITTER
Tweets by @koalatracker
Recent Posts

  • We're talking; they're dying
  • Queensland rolling back environmental protection
  • Wild koalas: slow life in the fast lane
  • We don't know what we don't know
  • Killer cows
  • The rise of ecotourism
  • Koalas are water guzzlers!
  • Nobody should be allowed to hunt endangered wildlife
  • Support
  • Citizen Science
  • How to find koalas in the wild
  • Going, going, gone...
  • A big day for koalas
  • An extraordinary situation
  • Koala orphans - Guest Post by Anika Lehmann, Moreton Bay Koala Rescue
  • The Problem with Disease is that it Spreads
  • People v Powerlink
  • Why Bother? Australian wildlife are simply pests


TAGS

killer cows tourism Koala map find koalas in the wild koaladiaries kangaroos violence animal cruelty kyogle koalas eating apples sick koalas koala's economic contribution queensland koalas australian koala koalas eating termites koala disease cows kill koalas what do koalas eat? koalas ecotourism sustainability koala conservation koalas drinking water koala mapping wildlife koala research intellectual property

Copyright Alex Harris © 2009-2016. All rights reserved. Designed by KoalaTracker Creator Alex Harris | Disclaimer 
Photos available under Creative Commons Attribution-Noncommercial 2.5 Australia License. Attribution: www.koalatracker.com.au member photo.


koalatracker koala tracker k-tracker koalatracker koala tracker koala tracker koala tracking koala tracking koala mapping mapping koalas koala map national koala tracker national koala mapping national koala database national koalatrakcer koala tracker k-tracker koalatracker koala tracker koala tracking koala tracking koala tracker tracking koalas mapping koalas scientific research tracking koalas mapping koalas ktracker ktracker koala tracker koala tracker
koalatracker koala tracker k-tracker koalatracker koala tracker koala tracker koala tracking koala tracking koala mapping mapping koalas koala map national koala tracker national koala mapping national koala database national koalatrakcer koala tracker k-tracker koalatracker koala tracker koala tracking koala tracking koala tracker tracking koalas mapping koalas scientific research tracking koalas mapping koalas ktracker ktracker koala tracker koala tracker